Officially connected to the grid!!

2023-07-19

At 20:10 on June 30, Xiwuzinduqin Banner Yinman Mining Co., Ltd. distributed new energy wind power project won the approval letter of Inner Mongolia Power (Group) Co., Ltd. Xilin Gol power Supply Branch to join the grid, and officially entered the grid connection start-up and commissioning stage.

At 15:50 on July 1, Yinman Mining completed multiple charging tests for each high-voltage equipment and entered the comprehensive debugging of the fan and system.

At 16:49 on July 2, after the comprehensive debugging of the fan and system, the No. 1 fan of the decentralized new energy wind power project of Yinman Mining officially generated electricity. As of July 4, all three turbines were put into power generation operation.

 

 

Xiwuzhumuqin Banner Yinman Mining Co., Ltd. distributed new energy power generation project, located in Inner Mongolia Xilin Gol League Baiyin Chagan Yinman mining area. The total planned capacity is 20MW. The fan is connected to the 35kV switching-closing station of the wind farm through a primary 35kV line, and the 35kV switching-closing station of the wind farm is connected to the substation of the mining area through a primary 35kV cable.

The average annual wind speed measured at 70m and 10m height of the wind farm is 8.4m/s and 6.8m/s respectively. The average annual wind power density was 606.1W/㎡ and 313.8W/㎡, respectively. The average annual wind speed of the wind farm at 70m height is 8.4m/s, the average annual wind power density is 606.1W/㎡, and the wind power density is grade 5. The annual effective wind speed hours are 7968h (3m/s ~ 25m/s), the prevailing wind is 180° ~ 292.5° (S ~ WNW), the wind direction is stable, and the wind energy resources are abundant. It has high development value and is suitable for building large wind farms.

Yinman Mining decentralized new energy wind power project completed the "Decentralized New Energy power Generation Project Feasibility Study Report" in December 2021 and reviewed and filed; On August 4, 2022, Xilin Gol League Energy Bureau "Notice on Agreement to Xiwuzhumuqin Banner Yinman Mining Co., LTD. Distributed New energy power generation Project change Approval"; The project infrastructure will be started on September 25, 2022 and completed on October 25, 2022; The main machine will be installed on December 16, 2022, the line and switch station installation will be started on February 3, 2023, and the main machine installation will be completed on February 26, 2023. On May 25, 2023, the installation of the line and switch station was completed, and the commissioning and formalities of grid-connected power generation were fully entered, and the whole process of grid-connected power generation was finally completed on June 30, 2023.

 

 

The project is designed in accordance with the principles of rational use of resources and improvement of energy efficiency, and in strict accordance with the national standards for rational use of energy and energy-saving design codes. The design concept of "energy saving, ecology and economy" should be implemented in the selection of the onlooker site selection of the wind farm, the overall layout and design scheme comparison of the wind farm, the selection of the wind generator set and the selection of related energy consumption equipment. The requirements of energy saving and ecological environmental protection should be fully considered in the selection of the design scheme, equipment and materials, and the new emissions should be reduced as far as possible to achieve the purpose of wind farm construction. The project is constructed as a "resource saving and environment friendly" project. The content of the project is in line with the national laws, regulations and industrial policies on energy conservation, the energy consumption index is in line with the industry access conditions, and the rational energy use standard and energy-saving design plan.

The process equipment of the project uses transformers, box-type transformers, lighting fixtures and other high-efficiency and energy-saving products recommended by the state. The energy consumption indicators of the main energy-consuming equipment, process equipment and transformers of the project exceed the maximum energy consumption quota of the relevant standards stipulated by the state. The project does not adopt the outdated technology and equipment that is prohibited or eliminated by explicit decree.

The energy consumption of the project is mainly electricity, because the main product of the project is also electricity, the power consumed is mainly for the wind farm plant electricity and various losses of electrical equipment. Its energy consumption accounts for a very small proportion of the total energy consumption in the local area, and has little impact on the total energy consumption and the completion of energy conservation targets in Inner Mongolia, which meets the requirements of energy conservation planning in Inner Mongolia.

Yinman Mining's decentralized new energy wind power project is officially connected to the grid, which is a solid step for Xingye Yinxi to "become a safe, green and sustainable resource-based enterprise model". Yinman Mining's decentralized new energy wind power project is officially connected to the grid, which is a strong promotion of Xingye Yinxi's "clean and green" energy to help the enterprise's "green development" goal, and will surely become a strong engine for igniting Xingye Yinxi's high-quality development in the next three years.